November 19, 2026
Why would a town schedule road construction in Hingham Centre to start in April, when four to six months of work will run through graduation season and the Fourth of July parade? The roundabout at Main, Middle and Short streets is being built with a $1 million award from MassDOT's Complete Streets program. That award expires on December 31, 2027, and the town has to spend the money before then to be reimbursed, as South Shore News reported in September.
The rest of the schedule follows from that date. It also means the project will be under construction in June, which is the month the intersection's own safety study singled out.
On September 15, 2026, the Select Board voted 3-0 for an $86,500 design amendment with a not-to-exceed figure of $198,700. That money pays the town's traffic engineering consultant to finish the design, get the project ready for bidding and handle quality assurance during construction. It comes from state Chapter 90 road funds, with roughly half in fiscal 2027 and the rest in fiscal 2028. Construction itself is paid for by the Complete Streets award. The town won that award after submitting a design that was about 95 percent complete.
The expiration date drives each step that comes before it:
| Step | Planned timing | What happens |
|---|---|---|
| Design complete | Mid to late November | Consultant finishes plans for bidding |
| Bidding | Late December or early January | Water main and roundabout go out as one contract |
| Contract signed | February | Contractor in place |
| Groundbreaking | April | Water crews start, road work follows |
| Construction | Four to six months from April | Runs into summer and the start of the school year |
| Award expires | December 31, 2027 | Money must be spent to be reimbursed |
All of these dates are plans. When Chair Liz Klein asked at the September meeting whether the work could be scheduled around the school year, she was told it could not.
The intersection has been under study for a while. In February 2024, the town's traffic committee reviewed a road safety audit by traffic engineers Vanasse & Associates, done after numerous crashes and near-misses. The audit looked at peak hours on weekday mornings, weekday evenings and Saturday middays. It also took into account the many bicyclists who ride through and the crosswalks that don't meet current Americans with Disabilities Act standards.
According to the Hingham Anchor's July 2025 report, the audit found that most of the crashes happened in June. It said that pattern "may include a high percentage of out-of-town motorists who are typically traveling to the nearby beaches or heading to vacation areas along the coast who are unfamiliar with the local roadways." The audit also pointed to young drivers, because Hingham High School is half a mile to the south and the intersection is the main route to the school.
A September 2025 Anchor report cited 19 crashes over five years, including a fatal motorcycle crash in 2021.
Put that next to the construction schedule. Construction starts in April and lasts four to six months, so the work zone will be active through June. That covers the end of the high school year, the start of beach traffic and the stretch the audit tied to most of the crashes. That is the trade-off for meeting the grant deadline. It is also the season residents will want to plan around.
Officials say the roundabout will be a single lane. Town Engineer J.R. Frey described it to the Anchor in 2025 as one approach lane and one exit lane in each direction, with a crosswalk on every leg.
The town chose it over a traffic signal and other options. According to South Shore News, a signal would have needed mast arms on Article 97 land and could have forced the town to take private property. The roundabout needed no taking, changed no Article 97 land and needed no special legislation, and it rated as both the safest and the most efficient option. Frey told the Anchor in 2025 that it could be built without a Town Meeting vote.
Frey also said that no part of the Town Common will fall inside the roadway or the curb line.
Getting to a roundabout took some public discussion. During the 2025 reviews, as the Hingham Anchor reported in September 2025, residents suggested other approaches, including long narrow islands and limits on some turns. That discussion also covered pedestrian safety and how fire trucks would get through. One idea was a textured or cobbled center island that larger vehicles could drive over.
For anyone who hasn't driven many roundabouts, Frey listed the steps in the town's own terms:
The project is larger than the intersection itself. The September design amendment adds the streets where water main work is planned, including an extension of Main Street and part of Levitt Street, plus lighter work on Short Street and School Street.
The water main has to be finished before the roundabout's final surface goes down. So the plan is one contract: Weir River Water System crews break ground in April, and road construction follows behind them. Frey said the water work could conceivably start earlier, but he didn't commit to that.
Select Board member Julie Strehle welcomed the coordination, as South Shore News reported:
"I just love to hear that when there's going to be a road construction project that you're teeing it up, lining it up with Weir River water system, that's living into the promise of owning our own water system and having control over that."
The Fourth of July parade passes through Hingham Centre. According to the Hingham Anchor's September 16 report, the contract will include language to limit disruption to the parade and to keep the affected roads passable. Select Board member Bill Ramsey asked that the contractor be required to keep the parade route passable and safe for spectators, and Frey said that requirement would go into the bid documents.
Frey addressed larger vehicles at the same meeting. He told the board that 18-wheelers will be able to get through the roundabout without detouring onto side streets, though some movements will be restricted. "For the most part, however, truck operators will follow pre-planned routes to avoid that intersection or find another way around," he said, as the Anchor reported. "The design will not require regular detours of heavy traffic onto any of the side roads."
He said the fire department doesn't expect problems getting the Quint or an ambulance through. Drivers ahead of those vehicles will need some education on how to get out of the way. "Once inside the roundabout, an ambulance could actually pass around another vehicle if necessary," Frey said. Signs will be placed so the Quint's overhanging bucket clears them. An engineer will be on site to make sure the work follows the plans and specifications in the funding agreement.
Under the current plan, nothing breaks ground in the Centre until April. Here are the next steps to watch for:
If your routine runs through Main, Middle and Short, now is a good time to try a backup route for the high school drop-off or the drive to the beach. Hingham has dealt with plenty of road work and will get through this one too. For more about the town, including how its winter rules work on private streets, see our Hingham neighborhood page and our post on Hingham's private-road plowing policy.
If you're planning a move near Hingham Centre in 2027 and wondering how a summer of construction could affect timing, showings or your commute, I'm glad to talk it through, no pressure. William Tierney is here when you're ready. Let's Connect.
Hingham
Hingham
Blog
A New Name, Same Local Expertise in South Shore Real Estate
While I am not a native of Cohasset, I am very entrenched here. I can find you the right house, bank, builder, school, yoga studio, and yes, even the freshest organic ingredients for a good meal.